Dont Make A Big Mistake When You Sign Your Claim or Certification

- By harrybendrodt077
Publish Date : 2021-05-18 10:07:55
Dont Make A Big Mistake When You Sign Your Claim or Certification

The Contract Disputes Act of 1978 ("CDA") contains a few simple requirements for claims over $100,000, including certification. Yet to this day contractors have consistently violated the certification requirements and, as a result, had their claims dismissed by the Boards and Courts. This is a big mistake that is easy to avoid. The mistake happened most recently in NileCo Gen'l Contracting, LLC, ASBCA No. 60912, Sept. 22, 2017. It seems as if a technology-crazed world sometimes refuses to use the most low tech machine of all-the pen-because the pen is just not electronically convenient. Government contractors should be lower tech when signing claims.

The CDA states that each claim for more than $100,000 must be certified to state that:

1. The claim is made in good faith;

2. The supporting data are accurate and complete to the best of the contractor's knowledge and belief;

3. The amount requested accurately reflects the contract adjustment for which the contractor believes the government is liable; and

4. The certifier is authorized to certify the claim on behalf of the contractor.

41 U.S.C. § 7103(b). These particular requirements are included in Federal Acquisition Regulation ("FAR") 33.207(c) and the disputes clause in every contract. The FAR also states that the certification may be executed by any person duly authorized to bind the contractor. Id. Although the Contract Disputes Act does not define the term "execute," the Boards of Contract Appeals have consistently held for at least 10 years that to "execute a Contract Disputes Act certification, there must be a signature by a certifier." "Signature" is defined in the FAR as the discrete, verifiable symbol of an individual which, when affixed to a writing with the knowledge and consent of the individual, indicates a present intention to authenticate the writing. This includes electronic symbols.

FAR 2.101

A failure to sign the certification as required strips the Court of Federal Claims or the Boards of Contract Appeals of jurisdiction to hear the claim and is not a correctable defect that can be corrected to restore the jurisdiction.

https://canvas.rice.edu/eportfolios/754/Gertha/Top_Recommended_SPLK1003_Exam_2021
https://canvas.rice.edu/eportfolios/754/Gertha/Top_Demanded_SPLK2001_Exam_2021
https://canvas.rice.edu/eportfolios/754/Gertha/Top_Recommended_SPLK3001_Exam_2021
https://canvas.rice.edu/eportfolios/754/Gertha/Top_Recommended_SY0501_Exam_2021
https://canvas.rice.edu/eportfolios/754/Gertha/Top_Rated_SY0601_Exam_2021

Here are four cases over the past ten years (the last of which cites a 1993 case), where a "pen and ink" signature would have saved the contractor from having its claim dismissed by the Board:

(1) NileCo Gen'l Contracting, LLC, ASBCA No. 60912, Sept. 22, 2017. The contractor merely used a typewritten signature block ("Anwar Ahmed Director"). The Board dismissed the claim even though the contractor claimed there had been a course of dealing permitting use of the typewritten signature block. The Board noted that the parties could not override the jurisdictional requirement of an executed certification through a course of dealing-and could not confer jurisdiction by agreement of the parties.

(2) ABS Dev. Corp., ASBCA No 60022 et al., Nov. 17, 2016. For some of the claims in the appeal, the contractor used several typewritings of a name (presumably typewritten by electronic means) purporting to be signatures. "A typewritten name, even one typewritten in Lucida Handwriting font, cannot be authenticated and therefore is not a signature. [also] The typewritten "//signed//" is not a signature because it cannot be authenticated. Anyone can type a person's name, there is no way to tell who did so from the typewriting itself." These documents were dismissed as unsigned certifications.

(3) Tokyo Co, ASBCA No. 59059, April 23, 2014. The claim was stamped "TOKYO COMPANY For general contracting & services Baghdad-Iraq Build 23 St. Al-Karadaa" above the typed words "General Manager of Company BENIAMEN MONADHIL." The Board held that a stamp bearing the company name, explaining what it does, and its address and the typed but unsigned name of the general manager "are not particularized and do not specifically identify the person executing the certification." Again, the claim was dismissed.



Category : general

Transcutaneous electrical nerve stimulation (TENS) for chronic pain: the opportunity to begin again

Transcutaneous electrical nerve stimulation (TENS) for chronic pain: the opportunity to begin again

- Transcutaneous electrical nerve stimulation (TENS) for chronic pain: the opportunity to begin again-Transcutaneous electrical nerve stimulation (TENS)


Top rated CIS-SAM Dumps Questions 2021

Top rated CIS-SAM Dumps Questions 2021

- Practice makes you perfect. Use Our practice questions and you will become an expert.you can get success with a lot of ease


An Introduction to Oracle VM

An Introduction to Oracle VM

- Oracle VM is the x86 server virtualization solution from Oracle, designed to be the best virtualization platform to run Oracle technologies. It is Oracles only


Passing The CCNA And CCNP: Cisco Home Lab FAQ

Passing The CCNA And CCNP: Cisco Home Lab FAQ

- There is a real revolution today among CCNA and CCNP candidates. More and more of you are turning your back on "router simulators" and putting your ow